EI Associates recently completed a special assignment to prepare isometric piping drawings for fabrication at Mallinckrodt Baker’s Phillipsburg, NJ facility. The project involved preparing detailed piping isometric drawings for pre-fabrication of connections to 30 vessels and 53 pipe headers. Further project requirements comprised:
Project Requirements:
1. Scope Involved Installation Of New Vapor Recovery System
2. Project Comprised Two Multi-story Buildings (Bldgs 98 & 101)
3. Detailed Piping Fabrication Connection Drawings:
a) Connections To 30 Vessels And 53 Pipe Headers
b) 250 Iso’s
4. Class I, Div. I Rated Area
a) Required Minimum Of Field Welds – Target Was Zero Field Welds
5. 1/8” Dimensional Accuracy
6. Project Schedule: Engineering Complete In 3 Months